Pembangunan Pintu Tol Jorr Pulo Gebang Tanggung Jawab Pengembang
.
photo Nurito - Beritajakarta.id

Toll Access Disturbs Pulogebang Terminal Operational

Jakarta Provincial Government has finished the infrastructure and facility for Pulogebang Terminal, East Jakarta. In fact, overpass operational which connects terminal to JORR toll is still obstructed by access opening from toll developer.

Access operational will give them advantage, then why they asked money for warranty

Developer asked Rp 4 billion as warranty to construct supporting infrastructure. However, Jakarta Dept. of Transportation assessed toll gate construction towards Pulogebang terminal is the responsibility of developer.

“Access operational will give them advantage, then why they asked money for warranty,” said Andri Yansyah, Jakarta Head Dept. of Transportation, Tuesday (2/16).

Pulogebang Terminal Exit Access Completed

Toll gate construction is needed since terminal is about to operate.

“We hope such warranty money can be eliminated for the sake of public interest,” he added.

Linked News
Popular News indeks
  1. Ragunan Zoo Expected to Welcome 80,000 Visitors for Eid al-Adha

    access_time09-06-2025 remove_red_eye365 personTiyo Surya Sakti
  2. Let's Celebrate Jakarta Future Festival 2025 at Taman Ismail Marzuki

    access_time11-06-2025 remove_red_eye362 personAldi Geri Lumban Tobing
  3. City Ready to Support Railway Transportation System in Bali

    access_time13-06-2025 remove_red_eye362 personBudhi Firmansyah Surapati
  4. Jakarta Future Festival 2025: Invitation to Contribute Developing Jakarta

    access_time12-06-2025 remove_red_eye349 personAldi Geri Lumban Tobing
  5. Healthy Lifestyle for Students is Good, Munjirin Says

    access_time09-06-2025 remove_red_eye284 personNurito

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik